Perenco mentioned Friday it has resumed pure fuel manufacturing on the Davy area in United Kingdom waters 5 years after shut-in.
“Earmarked for decommissioning following a number of failed restarts in 2021, Perenco UK has accomplished a complete revival venture with manufacturing from Davy wells A3 and A5 restarting in late April 2026”, Perenco mentioned in a press launch. “Mixed manufacturing from each platforms is now on-line and producing into Perenco’s Bacton terminal at a steady price of roughly 14 MMscf/d [million standard cubic feet per day].
“The excellent work program, which clearly demonstrates Perenco’s skill to securely lengthen area life, entailed a major simplification from the unique Nineteen Seventies’ design, in addition to materials tools upgrades, together with the set up of a wind turbine.
“As well as, partial decommissioning of non-productive wells has been achieved with the plugging and abandonment of two platform wells and a couple of subsea wells.
“The simplified Davy platform is now powered predominantly by wind vitality somewhat than diesel technology, so the operation is now persevering with with a decrease carbon footprint”.
Jo White, Perenco basic supervisor for the UK southern Noth Sea, mentioned, “Davy is ready to proceed to supply for a number of years to come back, and to function reliably and with decrease OPEX [operating expenditure] following the current work program”.
Earlier this 12 months Perenco accomplished the acquisition of Saturn Banks belongings already linked to Perenco infrastructure and which it plans to additional develop by way of the Bacton terminal on the Norfolk coast.
“The transaction concerned the acquisition of CalEnergy North Sea Ltd & CalEnergy Infrastructure Ltd, renamed Perenco SNS Ltd & Perenco UK Infrastructure Ltd, respectively, and the corresponding 50 p.c collaborating curiosity in, and operatorship of, the Blythe and Elgood licenses”, Perenco mentioned in an internet assertion April 8.
“Within the medium time period we’ll search for methods to boost manufacturing and cut back unit working prices, together with by bringing the Blythe H2 properly into our LAPS compressor inside the coming 12 months”, White mentioned, referring to the Lancelot Space Manufacturing System.
Based on Perenco’s announcement of the deal November 12, 2025, the plan for the acquisition features a additional Saturn Banks tieback to its current LAPS compressor on the Bacton terminal. The tieback would “enhance manufacturing charges, allow the restart of shut-in wells and lengthen the lifetime of the belongings”, Perenco mentioned then.
As of the November announcement, considered one of Blythe’s two wells and Elgood’s single properly have been shut in. Blythe, which has a usually unmanned platform, was on the time producing at a price of six million cubic toes by way of the opposite properly, Perenco mentioned. Elgood is a tieback to Blythe. Each fields began producing fuel 2022 by way of a brand new connection to the Bacton terminal by way of the reused Thames pipeline.
To contact the creator, e mail jov.onsat@rigzone.com
What do you suppose? We’d love to listen to from you, be part of the dialog on the
Rigzone Vitality Community.
The Rigzone Vitality Community is a brand new social expertise created for you and all vitality professionals to Converse Up about our business, share information, join with friends and business insiders and interact in knowledgeable group that can empower your profession in vitality.