Contractor Bechtel Vitality Inc. has turned over the primary prepare of the Corpus Christi LNG Stage 3 challenge to proprietor Cheniere Vitality Inc. following the completion of commissioning actions.
“The substantial completion of the primary prepare of CCL Stage 3 – forward of schedule and on finances – marks one other essential milestone for Cheniere and additional builds upon the observe document of excellence in execution constantly delivered by the Cheniere and Bechtel groups”, Cheniere president and chief govt Jack Fusco mentioned in an organization assertion Monday.
“We stay targeted on safely and effectively bringing the remaining CCL Stage 3 trains on-line forward of schedule, offering much-needed new LNG provide to the worldwide market, and creating long-term worth for our stakeholders by rising the Corpus Christi platform with disciplined, brownfield progress”.
Houston, Texas-based Cheniere mentioned, “As of January 31, 2025, general challenge completion for CCL Stage 3 was 78.3 %, which displays engineering 97.6 % full, procurement 97.2 % full, subcontract work 88.8 % full and development 45.5 % full”.
Stage 3’s prepare 1 had already began manufacturing December 2024 and dispatched its first cargo February 2025, the corporate mentioned earlier in its quarterly report.
Stage 3 could have seven midscale trains with an anticipated manufacturing capability of over 10 million metric tons each year (MMtpa), elevating the terminal’s capability to over 25 MMtpa from 10 trains.
Midscale trains 1-7 are permitted to export the equal of o 582.14 billion cubic ft a 12 months of pure fuel to each FTA and non-FTA international locations on a non-additive foundation. In 2021 the Division of Vitality (DOE) discontinued its observe of issuing separate long-term permits for the export of LNG from the identical facility. Stage 3’s export authorization lasts till December 2050.
Cheniere plans to construct two extra midscale trains adjoining to Stage 3 for an additional addition of about 3 MMtpa.
“We anticipate 2025 to be one other document 12 months for LNG manufacturing as Stage 3 trains are accomplished, and we look ahead to delivering monetary outcomes inside these ranges and additional enhancing the long-term worth proposition of Cheniere”, Fusco mentioned within the fourth-quarter report printed February 20, 2025. Final 12 months Cheniere exported a document 646 LNG cargoes, or 2.33 trillion British thermal models.
In April 2023 Cheniere utilized for authorization earlier than the Vitality Division to export LNG to FTA and non-FTA markets from the 2 proposed further liquefaction trains: midscale trains 8 and 9. In July 2023 Cheniere was cleared to export to international locations with a free commerce settlement with the US from the 2 proposed trains.
In January 2024, nonetheless, the Biden administration indefinitely paused pending allowing selections on the export of LNG to nations with out an FTA with the U.S.
Shortly after taking workplace for his second non-consecutive time period President Donald Trump withdrew his predecessor’s LNG export pause.
On March 11, 2025, a Reuters report cited Cheniere chief industrial officer Anatol Feygin as saying that the Federal Vitality Regulatory Fee had authorised the development of midscale trains 8 and 9.
To contact the creator, e mail jov.onsat@rigzone.com
What do you assume? We’d love to listen to from you, be a part of the dialog on the
Rigzone Vitality Community.
The Rigzone Vitality Community is a brand new social expertise created for you and all power professionals to Communicate Up about our trade, share data, join with friends and trade insiders and interact in an expert group that may empower your profession in power.